The bridge's piers and approach structure on the side facing Nguyen Hue walking street are nearing completion as they curve toward the main span.
The approach connecting the bridge to Ton Duc Thang Street stretches approximately 239 meters in length.
The design features a recirculating waterfall integrated directly into the structure.
It will also include a dedicated bicycle lane and is engineered to safely support ambulances weighing up to three tons.
Designated spaces on both sides of the bridge will allow pedestrians to rest, take photographs, and enjoy the surrounding views.

The approaches feature slender beams measuring just 25 cm thick.
This design choice creates a light appearance that complements the overarching water coconut leaf concept, while still meeting all structural and landscaping requirements.
The 187-m main span connecting the two bridge piers will feature a cable-stayed arch design, complete with a steel girder and a cross-section varying from 6 to 11 m in width.
The steel arch for the main span is being assembled on a construction platform at the Dai Dung Shipbuilding JSC factory, located in the Dong Xuyen Industrial Park in Rach Dua Ward, which is formerly part of Vung Tau City. Photo by Truong Ha
Viewed from above, the steel arch is taking form, showcasing the shape of a water coconut leaf.
The architectural concept was developed by a consortium comprising Chodai, Takashi Niwa Architects, and Chodai Kisojiban Vietnam.
The team's collaborative proposal previously secured the highest score in the project's official design competition. Photo by Truong Ha