The Cat Lai interchange opened in 2010 with two overpasses carrying left-turning traffic from Cat Lai Port, the country's largest, toward the city center along Nguyen Thi Dinh Street and Mai Chi Tho Boulevard, one overpass carrying left-turning traffic from the former Thu Duc City toward the port, and seven surface branches below.
The bridge branches, surface roads and metro line interweave to form a modern traffic network at the city's eastern gateway.

Also on Hanoi Highway is the Vietnam National University Ho Chi Minh City interchange, completed in 2019. The project runs nearly 2 km and includes one open-top tunnel and three overpasses, stretching from the entrance of Suoi Tien theme park to near the new Mien Dong bus station.
The open-top tunnel is more than 1 km long, with eight lanes and an 80 kph speed limit. Above it sit overpasses 17 m wide and 38 m long that allow vehicles to turn around.

After four years of construction, several components are already in use, including the overpass branch for right-turning traffic from the Long Thanh-Dau Giay Expressway down to Mai Chi Tho Boulevard, two bridge branches linking Mai Chi Tho with Dong Van Cong Street in both directions, and two underpasses on Mai Chi Tho that have helped ease local congestion.
Contractors are now concentrating on the section connecting Mai Chi Tho with the expressway and Luong Dinh Cua Street. The full project is scheduled for completion in the third quarter of 2027.
So far the project has delivered only a handful of components, including the Ky Ha 3 bridge, the left branch of My Thuy 3, an overpass and an underpass built between 2019 and 2021, which have eased congestion on the approach to Cat Lai Port.
Phase three broke ground in 2025 and covers the right branch of the Ring Road 2 overpass and the right branch of the Ky Ha 3 bridge, each with four lanes. Both are taking shape but have slipped behind schedule and are now pushed to 2027.
Once finished, the interchange will stand four levels high, cutting congestion and accidents in the area and helping meet freight demand at the Cat Lai port cluster.