The 725-meter-long, nearly 10-meter-wide steel flyover, which has two traffic lanes, is the project's most expensive component. It is designed to complete the four-level interchange and ease congestion at the entrance to Cat Lai Port.
The flyover curves from Nguyen Thi Dinh Street toward Vo Chi Cong Street. Construction is about 65% complete, with the structure expected to be finished in the first quarter of 2027.

Bridge piers and deck sections are taking shape on both sides, with contractors expecting to connect the remaining sections of the Vo Chi Cong flyover soon.