Four unfinished projects could put Christmas opening of Vietnam's largest airport Long Thanh at risk

While construction of its main facilities is being accelerated, the airport in Dong Nai City is running an Operational Readiness and Airport Transfer (ORAT) program of 55 scenarios, split into three rounds between September and December.

In a recent report to government leaders on the conditions for opening the airport, the Ministry of Construction said the Dec. 24 plan proposed by the Airports Corporation of Vietnam (ACV) would put the facility into use early, gradually bring returns on the investment and pave the way for the transfer roadmap.

But with large volumes of work still outstanding on some items, the ministry said the opening date should be weighed against actual results.

As of late October, three of the project's four components were on course to be ready for operation in December: the headquarters of state agencies (component 1), air traffic management facilities (component 2) and ground service facilities (component 4).

The biggest challenge lies in component 3, the airport's essential works. Of its 16 construction packages, four have been completed and 12 are under way.

According to ACV's schedule, the remaining work on some packages is still very large and risks delaying completion. These are the internal roads and technical infrastructure (package 4.8), the passenger terminal (package 5.10), Cargo Terminal 1 and auxiliary facilities (package 7.8) and the parking building (package 11.5).

The packages involve many complex items and are also held up by problems with construction material supplies and payments to contractors.

Some component 3 packages must be finished in November so that related items in components 1, 2 and 4 can be connected and accepted.

Their progress directly affects whether the airport can operate as an integrated whole. It is also a condition for ACV and regulators to complete environmental and aviation security licensing and other procedures.

Citing international practice and recommendations from the International Air Transport Association (IATA), the ministry said ORAT at a large, highly integrated new airport tests not just equipment but the operating capacity of the whole system.

Because such airports have many complex automated systems and require coordination among many parties, preparation and real-world testing usually take six to 12 months, with consecutive rounds of trials to find, fix and recheck faults.

The exterior of Long Thanh International Airports passenger terminal on Nov. 17. Photo by Quynh Tran

The exterior of Long Thanh International Airport's passenger terminal on Nov. 17, 2026. Photo by VnExpress/Quynh Tran

At Long Thanh, comprehensive integrated testing is expected to last about three months, from late September until commercial operations begin in December.

No real flights operate during this period, while ACV must speed up construction, acceptance checks and equipment calibration, complete procedures, assign staff and set operating processes.

The ministry said the short ORAT window would narrow the buffer for handling problems, especially faults that only emerge when many systems run together or with real passengers, baggage, cargo and aircraft.

It asked ACV, as the airport operator, to review and fully assess the plan to open in December. ACV is responsible for setting the timing, scope and plan for operations based on how fully the facilities are completed, acceptance and trial results, safety assessments and completed procedures.

To secure the December opening, Permanent Deputy Prime Minister Pham Gia Tuc has instructed the Ministry of Construction to direct ACV to draw up a plan that guarantees security and safety and is feasible, to be reviewed alongside an assessment of the conditions needed to open the airport.

The Ministry of Finance and other agencies were told to keep guiding and helping ACV resolve the project's payment problems.

On construction, ACV must closely review the remaining work on each package, set a completion deadline for each item and resolve problems with fuel and material supplies and payments for completed work.

It must also make contractors keep to schedule, and identify those responsible and take action against any that fail to.

ACV must also work with ministry units on procedures such as acceptance of completed items, inspection of operating conditions and licensing. Aviation-specific procedures must be finished on time so they do not delay the opening.

Government leaders also told Dong Nai and Ho Chi Minh City to keep reviewing their capacity to supply fuel and materials, giving priority to the airport, and to speed up completion of transport links to Long Thanh.

Under ACV's earlier plan, the airport will handle up to 366 flights a week in its initial phase, 322 domestic and 44 international.

A survey of airlines and other stakeholders by the Civil Aviation Authority of Vietnam found that all international carriers support moving to Long Thanh.

However, 34 of them want to delay the move from Ho Chi Minh City's Tan Son Nhat Airport until the winter 2027 flight schedule or later to have enough time to prepare. Some domestic airlines are ready to operate at the airport from its first phase under ACV's plan.

Long Thanh, set to be Vietnam's largest airport, covers about 5,000 hectares and is being built in three phases. The project is now in phase 1, designed to handle 25 million passengers and 1.2 million metric tons of cargo a year.