At the Bien Hoa-Vung Tau Expressway interchange, contractors have largely finished compacting the roadbed and are preparing to lay asphalt on the section being widened to 10-12 lanes.
A viaduct of about 300 m running parallel to the existing HCMC-Long Thanh Expressway has most of its girders in place and is expected to be finished by the end of this year.

Over the Dong Nai River, a line of Long Thanh 2 Bridge piers has risen alongside the existing bridge. The spans of the main bridge are scheduled to be joined at the end of this year, with completion in the first quarter of 2027.